Project Name |
Construction of Versova Bandra Sea Link (VBSL) on EPC basis |
Implementing Authority |
Maharashtra State Road Development Corporation (MSRDC) |
Project Location |
Mumbai (India) - Bandra to Versova |
Contractor |
M/s. Webuild–Apco JV (Webuild– 30%, Apco – 70%) |
Authority Engineer |
M/s Pentacle Consultants (I) Pvt Ltd JV with Nippon KOEI Ltd |
Authority Engineer SI |
M/s. Fortress Infracon Ltd |
System Integrator |
M/s. ABM Knowledgeware Ltd in Consortium with NTT Data Business Solutions Private Ltd |
Contractor’s Design Consultant |
M/s. Dar Al-Handasah Consultants (Beirut, Lebanon) |
Contractor’s Design Proof Consultant |
M/s. Spectrum Techno Consultant Pvt Ltd |
NGO |
M/s. Tata Institute of Social Science (TISS) |
Total Contract Value |
INR 6,993.99 Crores |
Contract Period |
60 months (Construction period) + 24 months (DLP) |
Appointed Date |
24 June 2019 |
Completion Dates |
26 December 2026 (Revised Completion of Construction Period) 26 December 2028 (Revised Completion of DLP) |