1 |
Forest Clearance Stage 2 dated 30.11.2021 |
Info Versova Bandra Sea Link Project |
30/11/2021 |
Download |
2 |
CA-Ms. Tata Institute of Social Science |
Info Versova Bandra Sea Link Project |
01/04/2021 |
Download |
3 |
CCF THANE Working Permission |
Info Versova Bandra Sea Link Project |
22/12/2020 |
Download |
4 |
IIT Traffic Survey Report for VBSLP |
Info Versova Bandra Sea Link Project |
12/11/2020 |
Download |
5 |
Amended CRZ Clearance for Versova Bandra Project |
Info Versova Bandra Sea Link Project |
02/11/2020 |
Download |
6 |
Information on Extension of VBSL Connectors up to WEH |
Info Versova Bandra Sea Link Project |
13/12/2019 |
Download |
7 |
Information on VBSLP-CA Link |
Info Versova Bandra Sea Link Project |
13/12/2019 |
Download |
8 |
10.10.2019_ltr to NEERI_Reg. Work Order of Juhu Koliwada Casting Yard |
Info Versova Bandra Sea Link Project |
09/12/2019 |
Download |
9 |
Information on Versova Virar Sea Link Project |
Info Versova Bandra Sea Link Project |
09/12/2019 |
Download |
10 |
Notifying the Appointed Date |
Info Versova Bandra Sea Link Project |
17/07/2019 |
Download |